Vermont Public is independent, community-supported media, serving Vermont with trusted, relevant and essential information. We share stories that bring people together, from every corner of our region. New to Vermont Public? Start here.

© 2024 Vermont Public | 365 Troy Ave. Colchester, VT 05446

Public Files:
WVTI · WOXM · WVBA · WVNK · WVTQ
WVPR · WRVT · WOXR · WNCH · WVPA
WVPS · WVXR · WETK · WVTB · WVER
WVER-FM · WVLR-FM · WBTN-FM

For assistance accessing our public files, please contact hello@vermontpublic.org or call 802-655-9451.
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Follow VPR's coverage of Vermont Yankee, from the archive and continuing through the plant's planned closure in 2014.Most Recent Reporting | From The Archive

Entergy Plans Radioactive Waste Transfer

Entergy Vermont Yankee has begun the process to gain regulatory approval to move spent fuel from a pool inside the reactor building to another area on the property.

Entergy wants to store the highly radioactive waste in steel and concrete casks on the plant grounds. But first it must construct a large, flat concrete pad to accommodate the new waste facility.

The company filed notice this week with the Town of Vernon and the Windham Regional Commission of its plans for the concrete pad. It plans to file a formal request with the state Public Service Board on June 30.

In a news release, Entergy said  construction would likely be finished by 2017, and all the spent fuel transferred by 2020.

John worked for VPR in 2001-2021 as reporter and News Director. Previously, John was a staff writer for the Sunday Times Argus and the Sunday Rutland Herald, responsible for breaking stories and in-depth features on local issues. He has also served as Communications Director for the Vermont Health Care Authority and Bureau Chief for UPI in Montpelier.